Work packages have been released on the icngateway for the Kidston Solar Project located on the old Kidston gold mine near Georgetown (pictured above) about 270km north-west of Townsville.
Phase one of the project is expected to generate 145GWh of electricity, which is enough to power more than 26,480 homes.
UGL has the EPC contract. Completion date is January 2018.
Open listings include:
- Fencing components – Open 31 Mar 17 :: Close 12 Apr 17
- Concrete Works – Open 31 Mar 17 :: Close 16 Apr 17
- Earthworks Equipment and Crane Hire – Open 31 Mar 17 :: Close 16 Apr 17
FURTHER ASSISTANCE
UGL strongly encourages local industry to contact the ICN Queensland in the first instance to improve their understanding of the EOI process.
UGL’s primary contact is:
Trevor Noble
Project Manager
E-mail: [email protected]