Bulk head gates restored

Ready for power station overhaul

Bulk head gates restored

Four massive bulk head gates were reinstalled at CS Energy’s Wivenhoe Power Station recently after being refurbished in a $1.1 million project.

Site manager Darren Kendrick said the 46-tonne steel gates performed a critical safety role during overhauls by isolating key areas of the power station to enable workers to safely carry out inspections and maintenance.

“As Wivenhoe is a pumped storage hydroelectric plant, we need to drain and isolate areas of the power station before people can do maintenance in there,” Mr Kendrick said.

“During overhauls, these gates slide down from their position above the power station tail bay to temporarily block water flow at our main intake and discharge points for Lake Wivenhoe.”

The gates were removed for refurbishment in December 2017 and transported back to the power station using eight semi-trailers for the gates and counterweights required for their reinstallation.

On arrival at the power station car park, two cranes were used to lift and reinstall the gates one at a time.

Mr Kendrick said the refurbished gates would be used during the upcoming overhaul of Unit at 2 at Wivenhoe Power Station from April to July this year.

“Wivenhoe Power Station has a design life of 100 years, so regular overhauls and maintenance will keep it operating in peak condition and providing electricity for many years to come,” he said.

PLEASE SHARE ON YOUR

LATEST NEWS

No Thumbnail

Tenders are sought for ex-Royal Australian Navy helicopters. The RAN is currently withdrawing it’s fleet of AS350BA Squirrel and is […]

READ MORE

The North Queensland Civil Construction Association has sought an undertaking from State Government that local contractors be given preference for […]

READ MORE

The mighty flow in the Flinders River this week has highlighted the potential power of a planned 400,000 megalitre dam […]

READ MORE